We're working on a kitchen renovation in a house built about
1900. The kitchen space has been gutted down to the studs and overhead joists and is nice and easy to wire with romex.
There are sufficient kitchen circuits to warrant a new sub-panel which will be located in the basement just below the kitchen. The basement has a plaster ceiling.
The question is how to handle the penetrations through the plaster ceiling and into the wall cavity above while maintaining a proper fire-stop.
At the main panel on the opposite side of the basement, the existing branch circuits run in romex going right into the ceiling and plastered right up to the romex. There is also older BX armored cable. I am comfortable with plastering around BX, but romex seems to be a different animal.
One way I can handle the penetration(s) up from the new sub-panel is with a short length of 2-inch conduit passing from the sub-panel through the ceiling and into the wall cavity above. A bushing would be used on the end of the conduit and the romex would be run in the conduit from the sub-panel and then fan out to the various outlets, switches and fixtures.
There are about 15 branch circuits for the kitchen and the question is how many 12/2 and 14/2 romex will fit into a 2-inch conduit and still comply with the NEC conduit fill limitations and not be so tightly packed as to require de-rating. I can do the calculation for individual #12 and #14 conductors but I don't know how to figure in the romex's outer jacket. And I seem to recall that the jacket on NM-B romex is rated at 60-degrees C even though the indivual conductors are rated at 90-degress C.
(Could the romex jacket be removed where it enters the conduit and just the inner conductors and ground run through the conduit and into the sub-panel if necessary?)
Suggestions on how to handle the floor penetration(s) for so many circuits while maintaining a proper fire-stop would be appreciated. Thanks.
Bear