| KVA demand charges do take into account power factor (by the way I believe | that tyou meant less than 1 not less than 0) The energy seen by a KWH meter
Yes, I meant less than one. Sorry about that.
| is unchanged as you indicate - except that, at any power factor except | unity the current, at a given voltage will be higher than the minimum | required to produce power. 1)the losses will be higher - customer pays more | in energy charges.
If your power factor is 1.0, you're not wasting any more power than in the proportion to what you use, relative to the efficiency of the whole system.
| 2)( and this is more important) the heating of the utilities transformers, | lines, generators, etc will be higher and such equipment must be sized on | the basis of KVA, not KW.
And of course this extra waste has two components. The facility cost to scale it up to be able to slosh the power around for the customer's sloppy load, and the energy lost while sloshing it around.
| Poor power factor costs the utility (a 2.5 KW load at 0.5 pf is a 5KVA load | as seen by the transformer and it must be sized accordingly), and this cost | is passed on to the customer with such a poor power factor (or poor load | factor) in the form of demand charges based on KVA. This is not done for | residential customers as it is simply cheaper and easier to take into | account typical residential pf in the rate structure.
As long as the demand charges relate ONLY to physical facility capacity costs, then that is the right thing to do. The loss of energy due to the inefficiency (small percentage) in transmission and distribution should also be paid for by the customer that insists on doing that, but it should be based on actual usage; a demand figure doesn't measure this part.
| 3) Poor pf -lagging- can cause excessive voltage drops. excessive leading | vars can also cause problems. | | No myths, either urban or otherwise are involved- just economics.
I think the myth is that all one has to do is get their current and voltage to be out of phase by 90 degrees relative to each other and the classic home power meter won't measure it. To whoever believes that then I suggest going all the way to 180 degrees and run the meter backwards so the power company pays you to use their electricicty :-)
Of course, none of that is real.
| It is then often advantageous for commercial and industrial customers to | provide some pf compensation - and this is done. Correction to exactly unity | pf is not done nor is it economic- There is an optimum point but few bother | with the calculation of such an optimum in design..
The problems I run into in designing and build computer data centers is more a harmonic issue. But even then there are phasing issues as many computer power supplies have narrow current spikes and are thus not evenly distributed over the AC cycle. One of the things I want to study is ways to balance such large non-linear loads (100's to 1000's of computers) so that current peaks do not get excessive (which can happen if all the power supplies work at the same part of the cycle, which tends to be true). I've started putting some thought into splitting things up into 6 or 12 phases. But then, that can also create lower power factor, too. Maybe balancing just how many of the various loads are sucking current at specific phase angles could approach making it look linear and unity.