We have recently adopted a different way of doing our revisions. The plan was, throughout the development and approval process, the Revision scheme would be alphabetic. When everything was approved, and the drawings were ready to be released for production, the Revision scheme would switch to numeric.
So, what we wanted was a scheme that went A, B, C until it was approved. Then switch to 1, 2, 3 for production released drawings. Before adopting this method, I tested SW to make sure it could in fact perform this way. IT DID!
So, now I just finished my first project with this scheme. All the drawings have alphabet revisions. Most of them are currently at A and some of them are at B. Now, when I go to switch the scheme to numeric, it wants to start with the next number after the equivalent alpha number.
For example, if the drawing is currently Revision A, I change the scheme and add a revision and it adds Revision 2 instead of 1. Or if the drawing is currently Revision B, I change the scheme and add a revision and it adds Revision 3 instead of 1.
I know that I tested this, and it DID perform the way I wanted it to. But now it is not. I know I'm not crazy. Does anyone have any clues what I may be doing different? I can't figure it out.