Hi!
Have a project with the following.
1 CPU 315F-2 PN/DP (Station Address 2) 1 MP 277 8" TOUCH (Station Address 3) 1 OP 73 (Station Address 1)When downloading project to the MP 277 I manually have to exit RT. That insn't necessary when I download to the OP 73. Siemens says it should be possible. When using Ethernet the RT exit automagically. But that isn't possible to use in the field when commissioning.
Using WinCC flexible 2005 SP1
Regards
-- Daniel