SCADA implementation project plan

Hi all,
does anyone have a project plan template regarding a SCADA system implementation (design, develop, configure, test and release
activities)?
thanks in advance, Nicola
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload

No, sorry. What project plan templates have you got?
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload
Hi,
what I need is a template of a project plan in which all activities required by a SCADA implementation are listed and, maybe, a timing of these activities.
Thanks, Nicola
operator jay ha scritto:

Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload
nmenicon wrote:

Googling for scada implementation project plan yields http://members.iinet.net.au/~ianw/pmp.html

Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload
Hi,
first of all thank you, this is pretty much what I was searching for.
At the moment, we are supporting our customer in the pre-qualification phase and, at the same time, we are writing a detailed design document that will be attached to the following tender.
Within this technical attachment we are required to define a transition plan because we are going to substitute the old SCADA with a new (modern) one. I think that part of this transition plan should describe design, acquisition and closout phases you described.
Do you even have an example of global WBS detailing all activities within these phases?
thanks in advance, Nicola
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload